Tuesday, November 15, 2011

Schedules

Materials Schedule

Item
Description
QTY
Size
Remarks
1
Trex Railing Post Sleeve
32
4 x 4 48”
Placed every 5 feet along the promenade
2

Trex Square
Baluster Kit
960
1 3/8" x 1 3/8" x 32"
Placed every 6 inches between each post
3
Trex Post Sleeve Skirt
14
4 x 4
1 placed on the bottom of each post
4
Trex Top and Bottom Rail Kit
2
6’
Needed to build railing along the top and bottom
5
Trex Post Sleeve Cap
14
4 x 4
Placed on the top of every Railing Post Sleeve
6
Footing and Post Anchors
120
8” diameter, 1’ deep
Placed every four feet on each side of the promenade and down the middle
7
Beam
120
8’
Two connected to the footings, one on each side. They will be placed all along the outside of the promenade (lengthwise), as well as in the middle.
8
Rim Joist
60
8’
One placed along the outside of the promenade (lengthwise), as well as in the middle.
9
End Joist
4
10’
Two will be placed at each end of the promenade.
10
Joist
160
10’
One placed every two feet to support the promenade.
11
Decking
1300
1” x 5.5” x 6’
Placed along the promenade to create the final deck on top.



Item
Description
QTY
Size
Remarks
12
Joist Hanger
320
10D Nails
Holds joists (item 10) to rim joists (item 8)
13
Common Nail Ring Barb Shank
2560
10D, 9 Gauge
8 per joist hanger (item 12)
14
Angle Brackets
8
2x6
Attached to corner joists for extra support
15
Fasteners
7800
10D Nails
Two nailed into every piece of decking into each joist it passes. ¾ to 1 inch from the edge of the board
16
Shim
120
½” thick
Pressure-treated, installed between beam and one side of anchor at each footing (item 6)
17
Nails
360
3-8D
Attach rim joist (item 8) to beams (item 7) nailed diagonal to each other
18
Screws
508
#12x3”
Attach top cap to 4x4 rail post with 2, screw every foot; attach top rail to 4x4 posts with 2 screws



Sample Decking and Railing to be Used


Landscaping Schedule
Item
Description
QTY
Remarks
1
Amelanchier canadensis-Shadblow Serviceberry
5
To be placed between the bike path and road along the edge of the chapel
2
Rhus glabra-Smooth Sumac
2
To be placed at the two corners behind the chapel
3
Cornus florida-flowering dogwood
6
Three placed on each side of the chapel along the windows
4
Helianthus angustifolius-swamp sunflower
8
Two placed between each tree planted along the sides of the chapel


Amelanchier canadensis-Shadblow Serviceberry

Rhus glabra-Smooth Sumac

Cornus florida-flowering dogwood

Helianthus angustifolius-swamp sunflower
Groundwork Schedule

Item
Description
QTY
Size
Remarks
1
Land Fill
70,000 ft3
N/A
Used to fill the uneven land along the coast.
2
GSE NW 8
8 oz non-woven geotextile
6,000 yd2
8 oz/yd²
Will be used under the gravel in the parking lot. Allows for filtration, drainage, and stability in the wet environment.
3
Gravel
9,000 ft3
N/A
To be used to fill the existing gravel parking lot
4
Blue Stone
590 ft²
N/A
Will be placed from the parking lot to the chapel to create a pathway.