Log Date: December 20, 2011
Marking Period 2
Green Pier
Work Started
- Final steps of construction-Finishing up schedules of fill and gravel
- My CAD drawing is now completely finished. Everything is included-dimensions, elevations, and all components.
- Schedule of land fill is finished. I calculated that we will need 69, 985 cubed feet of fill to level the land by the coast. For purchasing purposes, we would round this to 70, 000 to account for erosion since we surveyed and any mistakes we could have made.
- Follow rubrics.
- Stay on schedule.
- Consult mentors and other group members before making any major changes.
- Midterm needs to be started-it is very lengthy and its due date is approaching.