ED
Log Date: December 9, 2011
Marking Period 2
Green Pier

Work Started
  • Topography lines-I started drawing the lines of the current elevations of the land now.  This will help me calculate the amount of fill I will need to complete construction on my part of the design. I have been speaking to my mentor about it because this is the first time I have ever done anything like this before.
Work Completed
  • Press Release-My press release is completely finished and printed. I am handing it in today.
Reminders
  • Continuously update mentors about project. Remember that we need 10 mentor contacts by the end of the marking period.
  • Check with group members about what they are doing too. We need to stay constant with what they are doing.
  • Complete drawings with as much detail as possible because these will count as our construction part of the project.  We are not constructing anything until the third marking period, when we make our final model of the finished site.
  • Keep constant with calendar. I made that at the beginning of the marking period to remain constant with what I am doing. I have done fairly well so far.
  • Abide by all rubrics to avoid bad grades.